Construction of Biogas Plant in Surrey

West London AD Facility, Surrey

Reinforcec Concrete Basement Walls and slabs for Biogas Plant in Surrey

5.5m deep reinforced concrete basement with underground tanks

100m3 underground reinforced concrete leachate tank

30m long biofilter

5000m2 of running areas

1500m2 silage clamp with RC retaining walls 

Concrete pouring of waste to energy plant in Surrey 

 

Size of site:2.6 hectares
Input:Up to 85KT of solid and liquid packaged and unpackaged food waste
Digesters:4No. 4,200m3
Storage:4,200m3
Power Output:2.4MWe
Commissioned:January 2014
Construction period9 months

 

Construction of Reinforced Concrete Suspended Slabs for Renewable Energy Plant in Surrey